Q1 a) Pexp = (Popt + 4*Pmost + Ppess)/6 = (6+4*8+8.5)/6 = $7.75/lb b) Pexp = (Popt + 4*Pmost + Ppess)/6 = (21+4*24+30)/6 = 24.5lb/ c units c) Expected exist = 7.75 * 24.5 = $189.88 Q3 a) follow reckon = 1.85*(780+56) + 1.25*(142) + 1.10*(87+34+385) = 1546.6 + 177.5 + 556.6 = $2,280.70 b) 2281* 2.25 = $5132 No witness result not be approved $5132 is great than $4995 c) Need to steadfast up estimates for order of magnitude and budget items, and revise estimates in the beginning insure can proceed. Q4 The purport devise is very burning(prenominal) because without a blueprint, it is impossible to know where we be going or to judge how we are doing at acquiring there on a exteriorize. The primary parts of the plan are the budget, the schedule, and the force of details that fill these out. Planning covers two importa nt rudiments of the project namely work breakdown structure (WBS) and cost estimates. The WBS is the basic tool employ in project planning, and project estimates are typic everyy derived from the details found in the WBS. Estimates form the basis for defining project budgets. Accurate estimates are essential if budgets are to be keep during project execution.
Inaccuracies in estimates translate into cost variances during implementation, with resulting frustrations of project plan revisions, damage to project integrity, and possible early termination. Q5 Groundwater Cleanup device 1 Design 1.1 Evaluating several alternat ives 1.2 Preparing abstract design ! 1.3 Evaluating conceptual design 1.4 rig final design 2 evocation Preparation 2.1 Prepare specification 2.2 Pre-qualify installation contractors 2.3 Review all bids 2.4 Execute contracts 2.4.1 Recovery wells 2.4.2 Piping 2.4.3 word equipment 2.4.4 Start-up 3 Performance monitoring 3.1 Sampling...If you want to get a enough essay, order it on our website: BestEssayCheap.com
If you want to get a full essay, visit our page: cheap essay
No comments:
Post a Comment
Note: Only a member of this blog may post a comment.